Completed Projects
 
Project  
 
  Pipecams Purchase
Bond   No
CIP Line   39
Design Firm   N/A
Contractor   Environ. Products
Bid Opening   N/A
Construction Start   N/A
Construction Finish   04/30/11
Awarded Dollars   $75,000
Budget Dollars   $100,000
 
  McAfee Water Tank Repair /
  Painting
Bond   Yes
CIP Line   6
Design Firm   DWM
Contractor   Task Pro, Inc
Bid Opening   12/02/10
Construction Start   03/03/11
Construction Finish   07/08/11
Awarded Dollars   $467,941
Budget Dollars   
Picture Gallery
 
  Hammer Mill 3 Lift Station
Bond   No
CIP Line   47
Design Firm   HDR
Contractor   Lakeshore Eng.
Bid Opening   10/06/10
Construction Start   03/03/11
Construction Finish   07/08/11
Awarded Dollars   
Budget Dollars   


 