| Project |
|
| |
| Pipecams Purchase |
| Bond |
No |
| CIP Line |
39 |
| Design Firm |
N/A |
| Contractor |
Environ. Products |
| Bid Opening |
N/A |
| Construction Start |
N/A |
| Construction Finish |
04/30/11 |
| Awarded Dollars |
$75,000 |
| Budget Dollars |
$100,000 |
|
| |
McAfee Water Tank Repair / Painting |
| Bond |
Yes |
| CIP Line |
6 |
| Design Firm |
DWM |
| Contractor |
Task Pro, Inc |
| Bid Opening |
12/02/10 |
| Construction Start |
03/03/11 |
| Construction Finish |
07/08/11 |
| Awarded Dollars |
$467,941 |
| Budget Dollars |
|
| Picture Gallery |
|
| |
| Hammer Mill 3 Lift Station |
| Bond |
No |
| CIP Line |
47 |
| Design Firm |
HDR |
| Contractor |
Lakeshore Eng. |
| Bid Opening |
10/06/10 |
| Construction Start |
03/03/11 |
| Construction Finish |
07/08/11 |
| Awarded Dollars |
|
| Budget Dollars |
|
|